Powered by GoogleTranslate

Inspection Detail

Inspection: 110132693 - Harper Electric Construction Co., Inc.

Inspection Information - Office: Jacksonville Area Office

 

Inspection Nr: 110132693
Report ID: 0419700
Date Opened: 04/19/1993

Site Address:
Harper Electric Construction Co., Inc.
4 Miles Southwest Of Jay, Florida
Jay, FL 32565

Mailing Address:
P. O. Box 698, Andulusia, AL 36420

Union Status: NonUnion

SIC:1623

NAICS: 0 


Inspection Type: Accident

Scope: Complete

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 04/20/1993

Planning Guide: Safety-Construction

Emphasis:

Case Closed: 10/13/1993


Related Activity
Type Activity Nr Safety Health
Accident 360448153
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 3 1 4
Current Violations 3 1 4
Initial Penalty $5,750 $0 $0 $0 $0 $5,750
Current Penalty $5,750 $0 $0 $0 $0 $5,750
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001A Serious 19260059 E01 08/26/1993 09/08/1993 $750 $750 $0 -  
2. 01001B Serious 19260059 H 08/26/1993 09/08/1993 $0 $0 $0 -  
3. 01002 Serious 19260550 A15 I 08/26/1993 09/03/1993 $2,500 $2,500 $0 -  
4. 01003 Serious 19260550 A15 IV 08/26/1993 09/03/1993 $2,500 $2,500 $0 -  
5. 02001 Other 19260020 B01 08/26/1993 09/28/1993 $0 $0 $0 -  

Investigation Summary

Investigation Nr: 14331656
Event: 04/14/1993
ELECTRIC SHOCK - CONTACT WITH OVERHEAD LINE THRU BOOM

A three-person power line crew arrived at a worksite in a farm field. Their employer, a power line contractor, had the job of replacing utility poles. A four-conductor, 45-kilovolt overhead power line was supported by the existing poles. The crew's assignment was to spot the new poles on the ground where they were to be placed. The foreman directed the ground worker (who had 6 month's experience at his job--all with this employer) and the truck crane operator to position the crew's two trucks under the power line, where the new poles had been unloaded by the supplier, and to wait for further instructions. The foreman was going to inform them by radio of what size poles he would need. He then proceeded along the line to a site about 100 yards from the trucks. The crane operator mounted the truck from the rear to reach the operator's station. The ground worker was standing on the right side of the truck near the rear wheels and next to the new poles. The operator raised the boom up between 2 and 4 feet and swung it to the right. The hook on the load line was located directly over the stack of poles. Unfortunately, the boom had contacted the power line. The crane operator saw the ground worker fall to the ground. The operator lowered the boom, tried to help the injured employee, and called his foreman on the radio. The foreman and the crane operator transported the ground worker to the hospital, where he was pronounced dead. He had been electrocuted.

Keywords: OVERHEAD POWER LINE, ELECTRICAL, BOOM, POWER LINE WORKER, CRANE BOOM, POTENTIAL GRADIENT, ELECTROCUTED, E PTD, ELEC UTILITY WORK, CRANE

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 110132693 Fatality Electric Shock Laborers, except construction
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.

Close