Powered by GoogleTranslate

Inspection Detail

Inspection: 107829574 - Ertel Construction Co.

Inspection Information - Office: Sc Department Of Labor, Licensing, And Regulation

 

Inspection Nr: 107829574
Report ID: 0454510
Date Opened: 06/29/1989

Site Address:
Ertel Construction Co.
Race Track Rd
Lancaster, SC 29720

Mailing Address:
4324 Wallace Neal Rd, Charlotte, NC 28219

Union Status: NonUnion

SIC:4899

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 10/03/1989

Planning Guide: Safety-Construction

Emphasis:

Case Closed: 07/06/1990


Related Activity
Type Activity Nr Safety Health
Accident 360283402
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 3 1 4
Current Violations 3 1 4
Initial Penalty $2,340 $0 $0 $0 $0 $2,340
Current Penalty $2,340 $0 $0 $0 $0 $2,340
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100268 C 10/17/1989 10/26/1989 $810 $810 $0 11/03/1989 F - Formal Settlement  
2. 01002 Serious 19100268 I01 10/17/1989 10/20/1989 $720 $720 $0 11/03/1989 F - Formal Settlement  
3. 01003 Serious 19100268 N01 I 10/17/1989 10/20/1989 $810 $810 $0 11/03/1989 F - Formal Settlement  
4. 02001 Other 19100132 A 10/17/1989 10/20/1989 $0 $0 $0 11/03/1989 F - Formal Settlement  

Investigation Summary

Investigation Nr: 675025
Event: 06/21/1989
ELECTRIC SHOCK - DIRECT CONTACT WITH OVERHEAD LINE

A CREW OF EMPLOYEES WAS INSTALLING CABLE TELEVISION CABLE ON UTILITY POLES THAT WERE OWNED BY AN ELECTRIC UTILITY AND THAT SUPPORTED AN EXISTING 7200-VOLT OVERHEAD POWER LINE. THE SUSPENSION STRAND FOR THE CABLE HAD BEEN INSTALLED SEVERAL DAYS EARLIER, BUT IT HAD NOT BEEN GROUNDED. TWO EMPLOYEES WERE USING A CABLE JIG TO PULL THE CABLE ALONG THE SUSPENSION STRAND. ONCE THE CABLE WAS LAID OUT ALONG THE UTILITY POLES, IT WAS LASHED TO THE SUSPENSION STRAND. AS THE EMPLOYEES WERE PULLING THE CABLE, THE JIG FELL FROM THE STRAND. ONE OF THE EMPLOYEES THEN CLIMBED ONTO A NEARBY HOUSE TO REPLACE THE JIG. THE HOUSE WAS LOCATED BENEATH THE OVERHEAD POWER LINE AND THE SUSPENSION STRAND, AND THE TOP OF THE ROOF WAS ABOUT 4 FEET FROM THE POWER LINE. THE EMPLOYEE'S HARD HAT FELL OFF WHILE HE WAS CLIMBING, AND HE LEFT IT OFF WHILE HE REINSTALLED THE JIG. AS HE STOOD UP AFTER REPLACING THE JIG, HIS HEAD CONTACTED THE OVERHEAD POWER LINE. THE EMPLOYEE RECEIVED AN ELECTRIC SHOCK, WHICH KNOCKED HIM TO THE GROUND, MORE THAN 10 FEET BELOW. THE EMPLOYEE WAS ELECTROCUTED. HE WAS NOT WEARING HIS HARD HAT, FALL PROTECTION EQUIPMENT, OR ELECTRICAL PROTECTIVE EQUIPMENT AT THE TIME OF THE ACCIDENT, AND HE HAD NOT BEEN TRAINED.

Keywords: HARD HAT, OVERHEAD POWER LINE, ELECTRICAL, TELECOM WORK, E TC, ELECTROCUTED

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 107829574 Fatality Electric Shock Misc. electrical & electronic equipment repairers
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.