Powered by GoogleTranslate

Inspection Detail

Inspection: 106447691 - Savannah Electric And Power Co.

Inspection Information - Office: Savannah Area Office

 

Inspection Nr: 106447691
Report ID: 0418400
Date Opened: 04/19/1995

Site Address:
Savannah Electric And Power Co.
Bay Street At Jefferson Street
Savannah, GA 31401

Mailing Address:
600 E. Bay Street, Savannah, GA 31402

Union Status: Union

SIC:4911

NAICS: 0 


Inspection Type: Accident

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 05/17/1995

Emphasis:

Case Closed: 05/01/1996


Related Activity
Type Activity Nr Safety Health
Accident 360821458
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 2 2
Current Violations 2 2
Initial Penalty $3,225 $0 $0 $0 $0 $3,225
Current Penalty $3,225 $0 $0 $0 $0 $3,225
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100269 A02 IIC 05/23/1995 05/23/1995 $1,925 $1,925 $0 06/13/1995 R - Review Commission  
2. 01002 Serious 19100269 L06 III 05/23/1995 06/19/1995 $1,300 $1,300 $0 06/13/1995 R - Review Commission  

Investigation Summary

Investigation Nr: 596304
Event: 04/19/1995
BURN - ELECTRICAL FAULT ON OVERHEAD POWER LINE

A contractor had previously set a new utility pole next to an existing pole. Both wood poles were 65 feet in length. However, the contractor had set the replacement pole so that its top was about 28 inches below the old pole. On the day of the accident, three employees (two power line workers and one apprentice) climbed the pole, and two workers remained on the ground. The crew covered the 115-kilovolt overhead power line, transferred the overhead ground wire, installed the pole ground wire, and cut off a portion of the old pole. The crew then installed a temporary crossarm at the top of the new pole to enable them to lift the phase conductors. The crew decided to transfer the bottom conductor first. A new 6-foot-long, metal davit arm was installed on the new pole to support the bottom conductor. After installation, the davit arm was only about 26 inches from the energized conductor. The crew attached lifting blocks to the temporary crossarm and to a 4-foot lifting stick. The lifting stick was attached to the bottom phase conductor near the suspension insulator. The next step in the procedure was to pull the cotter key at the bottom of the insulator string to release the conductor. The apprentice power line worker was using an 8-foot-long A. B. Chance tie stick with a key puller attachment to remove the cotter key from the insulator string. The cotter key was facing away from the pole, and the employee was having difficulty removing it. The other power line worker had a live-line tool to turn the bottom bell. The clearance between the metal end of the lifting stick that was in contact with the energized phase conductor and the metal davit arm, which was at ground potential, was estimated to be about 12 to 14 inches. An arc-over occurred between the conductor and the metal davit arm, and fault current passing through the pole ground melted it and caused further arcing. The two power line workers lost consciousness. The apprentice line worker shook one of his unconscious coworkers, who quickly regained consciousness. The apprentice then patted out the flames of the burning tee-shirt on his other coworker, began pole-top rescue procedures on him, and lowered him to the ground. The apprentice and the other power line worker then descended the pole. A total of five employees were transported to a hospital. Two employees on the ground had rope burns on their hands from lowering the injured employee. The three employees on the pole had second- and third-degree burns and were hospitalized for their injuries.

Keywords: BURN, CLOTHING, ELECTRIC ARC, OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, LIVE-LINE TOOL, E PTD, ELEC UTILITY WORK, ELECTRICAL FAULT

Investigated Inspection
# Inspection Age Sex Degree of Injury Nature of Injury Occupation
1 106447691 Hospitalized injury Burn/Scald(Heat) Electrical power installers and repairers
2 106447691 Hospitalized injury Burn/Scald(Heat) Electrical power installers and repairers
3 106447691 Hospitalized injury Burn/Scald(Heat) Electrical power installers and repairers
4 106447691 Non Hospitalized injury Bruise/Contus/Abras Laborers, except construction
5 106447691 Non Hospitalized injury Bruise/Contus/Abras Laborers, except construction
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.