Inspection Detail
Inspection: 102254075 - B & B Electrical Contractor, Inc.
Inspection Information - Office: Oklahoma City Area Office
Site Address:
B & B Electrical Contractor, Inc.
10th And S. Peoria
Tulsa, OK 74135
Mailing Address:
409 N. Aspen, Broken Arrow, OK 74012
Union Status: Union
SIC:1623
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 10/12/1989
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 03/02/1990
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 360444467 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 4 | 4 | ||||
| Current Violations | 4 | 4 | ||||
| Initial Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| Current Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19040002 A | 12/08/1989 | 12/17/1989 | $0 | $0 | $0 | - | ||
| 2. | 01002 | Other | 19260059 E01 | 12/08/1989 | 01/12/1990 | $0 | $0 | $0 | - | ||
| 3. | 01003 | Other | 19260059 G01 | 12/08/1989 | 01/12/1990 | $0 | $0 | $0 | - | ||
| 4. | 01004 | Other | 19260059 H | 12/08/1989 | 01/12/1990 | $0 | $0 | $0 | - |
Investigation Summary
A SUPERVISORY POWER LINE WORKER AND ANOTHER EMPLOYEE WERE WORKING FROM A WOOD UTILITY POLE, MAKING CONNECTIONS ON A 4160-VOLT OVERHEAD POWER LINE. THREE OTHER EMPLOYEES WERE ASSISTING THEM FROM THE GROUND. THE TWO EMPLOYEES WERE TIED OFF AT THE TOP OF THE 35-FOOT POLE, WORKING ON THE WESTERN-MOST PHASE OF THE LINE. THE SUPERVISOR INSTALLED THE CONNECTOR ATTACHING THE JUMPER FROM THE DISCONNECT SWITCH TO THE LINE. THE OTHER EMPLOYEE ON THE POLE WAS INSTALLING THE JUMPER FOR THE LIGHTNING ARRESTOR. THIS EMPLOYEE THEN USED A TOOL TO CRIMP THE CONNECTORS. AS HE WAITED TO PASS THE TOOL TO HIS SUPERVISOR, THE SUPERVISOR REACHED OVER THE TOP OF THE ENERGIZED DISCONNECT JUMPER. HE REACHED BEYOND THE END OF HIS RUBBER INSULATING GLOVE, AND THE BOTTOM OF HIS EXPOSED UPPER ARM CONTACTED THE JUMPER. THE SUPERVISOR WAS ELECTROCUTED.
Keywords: ELEC PROTECT EQUIP, OVERHEAD POWER LINE, ELECTRICAL, POWER LINE WORKER, ELECTROCUTED, E PTD, ELEC UTILITY WORK, UTILITY POLE
| # | Inspection | Age | Sex | Degree of Injury | Nature of Injury | Occupation |
|---|---|---|---|---|---|---|
| 1 | 102254075 | Fatality | Electric Shock | Supervisors; electricians & power transm. install. |