Violation Detail
Standard Cited: 19100219 C04 II Mechanical power-transmission apparatus.
Inspection Nr: 957506.015
Citation: 01002
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $4,400.00
Current Penalty: $2,640.00
Issuance Date: 04/28/2014
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0418300
Contest Date:
Final Order: 05/29/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/29/2014 | $2,640.00 | Serious | ||
Penalty | Z: Issued | 04/28/2014 | $4,400.00 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.219(c)(4)(ii): The unused keyway(s) of projecting shaft end(s) were not filled up or covered: (a) On or about 02/05/2014 - Partition Department, #176 Akabono (Big Rotary), the keyway was not filled or covered.