Violation Detail
Standard Cited: 19100333 B02 II B Selection and use of work practices
Inspection Nr: 930523.015
Citation: 01002
Citation Type: Serious
Abatement Date: 02/05/2014 2
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 01/09/2014
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0420600
Contest Date:
Final Order: 02/04/2014
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/04/2014 | $7,000.00 | 02/05/2014 | Serious | |
Penalty | Z: Issued | 01/09/2014 | $7,000.00 | 02/05/2014 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.333(b)(2)(ii)(B): The circuits and equipment to be worked on were not disconnected from all electric energy sources: (a). While working on the Master Clad 15KV Switch Gear in the Motor Control Center (MCC) Switch Room, the equipment was not disconnected from its electrical energy source causing injuries to the employee as observed on or about August 16, 2013.