Violation Detail
Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 767103.015
Citation: 01013
Citation Type: Serious
Abatement Date: 06/30/2013 2
Initial Penalty: $4,200.00
Current Penalty: $2,100.00
Issuance Date: 05/30/2013
Nr Instances: 2
Nr Exposed: 1
Related Event Code (REC):
Gravity: 5
Report ID: 0213600
Contest Date: 06/13/2013
Final Order: 03/23/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | 2: Appeals Court | 03/23/2017 | $2,100.00 | 06/30/2013 | Serious | |
Penalty | C: Contested | 06/17/2013 | $4,200.00 | 06/30/2013 | Serious | |
Penalty | Z: Issued | 05/30/2013 | $4,200.00 | 06/30/2013 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: a) On or about 12/19/12 in the Core area; an extension cord was being used to supply power to relocatable power tap which was supplying power to the core cutter motor, a portable work light, a radio, and portable sander. b) On or about 12/19/12 in the Pallet stacker; an extension cord was being used to supply power to the control pedestal for the pallet stacker. Abatement Certification Required