Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311611081
Citation: 02024A
Citation Type: Willful
Abatement Date: 04/19/2010
Initial Penalty: $70,000.00
Current Penalty: $0.00
Issuance Date: 03/08/2010
Nr Instances: 1
Nr Exposed: 25
Related Event Code (REC):
Gravity: 10
Report ID: 0524700
Contest Date: 03/31/2010
Final Order: 09/27/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 09/27/2018 | $0.00 | Willful | ||
Penalty | Z: Issued | 03/08/2010 | $70,000.00 | Willful |
Text For Citation: 02 Item/Group: 024A Hazard: REFINERY
29 CFR 1910.119(d)(3)(ii): The employer does not document that the equipment in the process complies with recognized and generally accepted good engineering pra ctices: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not document the need for over pressure protection on pressure vessels as required by recogni zed and generally accepted good engineering practices. The Stripper Steam Reboiler (PR543538) is n ot protected by pressure relieving devices that would prevent the pressure insid e the vessel from rising above acceptable limits. Pursuant to 29 CFR 1903.19, wi thin ten (10) calendar days of the abatement date, the employer must submit docu mentation that it has abated the hazard. In addition, under 29 CFR 1903.19(e), t he employer must submit an abatement plan describing the actions it is taking to ensure that it is in compliance with the standards for all pressure vessels, in cluding documenting that each pressure vessel has been evaluated and is protecte d by pressure-relieving device(s) in accordance with recognized and generally ac cepted good engineering practices, such as the ASME Boiler and Pressure Vessel C ode. The abatement plan shall establish dates during the next three months when the evaluations and installations of overpressure protection shall be completed. Once the plan has been fully implemented, the employer must submit certificatio n of its full compliance with the standard.