Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311611081
Citation: 02012A
Citation Type: Willful
Abatement Date: 04/19/2010
Initial Penalty: $70,000.00
Current Penalty: $0.00
Issuance Date: 03/08/2010
Nr Instances: 1
Nr Exposed: 25
Related Event Code (REC):
Gravity: 10
Report ID: 0524700
Contest Date: 03/31/2010
Final Order: 09/27/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 09/27/2018 | $0.00 | Willful | ||
Penalty | Z: Issued | 03/08/2010 | $70,000.00 | Willful |
Text For Citation: 02 Item/Group: 012A Hazard: REFINERY
29 CFR 1910.119(d)(3)(ii): The employer does not document that the equipment in the process complies with recognized and generally accepted good engineering pra ctices: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not document that PSV-440 providing pressure relief protection to the Rerun Tower in the Alky Unit complies with recognized and generally accepted good engineering practices , in that, it has an inlet pressure drop greater than 3 PSV-440 was determined t o have an inlet pressure drop of 6.8 Pursuant to 29 CFR 1903.19, within ten (10) calendar days of the abatement date, the employer must submit documentation tha t it has abated the hazard. In addition, under 29 CFR 1903.19(e), the employer s hall submit an abatement plan describing the actions it is taking to ensure that it is in compliance with the standards including documentation that each pressure relief valve and associated piping for all process units have been evaluated and, if necessary, repaired or replaced to ensure inlet pressure drop is limited in accordance with recognized and generally accepted good engin eering practices, such as API Recommended Practice 520 and the ASME Boiler and P ressure Vessel Code. The abatement plan shall establish dates during the next th ree months when the evaluations, repairs, and replacements shall be completed. O nce the plan has been fully implemented, the employer must submit certification of its full compliance with the standard.