Violation Detail
Standard Cited: 19100119 D03 II Process safety management of highly hazardous chemicals.
This violation item has been deleted.
Inspection Nr: 311611081
Citation: 02002A
Citation Type: Willful
Abatement Date: 04/19/2010
Initial Penalty: $70,000.00
Current Penalty: $0.00
Issuance Date: 03/08/2010
Nr Instances: 1
Nr Exposed: 25
Related Event Code (REC):
Gravity: 10
Report ID: 0524700
Contest Date: 03/31/2010
Final Order: 09/27/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 09/27/2018 | $0.00 | Willful | ||
Penalty | Z: Issued | 03/08/2010 | $70,000.00 | Willful |
Text For Citation: 02 Item/Group: 002A Hazard: REFINERY
29 CFR 1910.119(d)(3)(ii): The employer does not document that the equipment in the process complies with recognized and generally accepted good engineering pra ctices: a.BP-Husky Refining, LLC - Oregon, Ohio: The employer does not document that PSV- 134 providing pressure relief protection to the Debutanizer Reflux Dru m in the Alky Unit complied with recognized and generally accepted good engineering practices in th at it has an inlet pressure drop greater than 3 PSV-134 was determined to have a n inlet pressure drop of 3.8 Pursuant to 29 CFR 1903.19, within ten (10) calenda r days of the abatement date, the employer must submit documentation that it has abated the hazard. In addition, under 29 CFR 1903.19(e), the employer shall sub mit an abatement plan describing the actions it is taking to ensure that it is i n compliance with the standards including documentation that each pressure relie f valve and associated piping for all process units have been evaluated and, if necessary, repaired or replaced to ensure inlet pressure drop is limited in acco rdance with recognized and generally accepted good engineering practices, such a s API Recommended Practice 520 and the ASME Boiler and Pressure Vessel Code. The abatement plan shall establish dates during the next three months when the eval uations, repairs, and replacements shall be completed. Once the plan has been fully implemented, the employer must submit certification of its f ull compliance with the standard.e