Violation Detail
Standard Cited: 19100119 E05 Process safety management of highly hazardous chemicals.
Inspection Nr: 280860.015
Citation: 01002
Citation Type: Serious
Abatement Date: 09/26/2012 2
Initial Penalty: $5,100.00
Current Penalty: $3,060.00
Issuance Date: 08/14/2012
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 5
Report ID: 0524500
Contest Date:
Final Order: 08/28/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/28/2012 | $3,060.00 | 09/26/2012 | Serious | |
Penalty | Z: Issued | 08/14/2012 | $5,100.00 | 09/26/2012 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.119(e)(5): The employer did not establish a system to promptly address the teams findings and recommendations; did not assure that the recommendations were resolved in a timely manner and that the resolution was documented; did not document what actions were to be taken; did not complete actions as soon as possible; did not develop a written schedule of when these actions were to be completed; The employer did not develop a written schedule of actions to be taken on recommendations and did not complete actions as soon as possible for findings and recommendations in the PHAs for both the Pekin Skid and the Decatur Skid.