Violation Detail
Standard Cited: 19100219 D01 Mechanical power-transmission apparatus.
Inspection Nr: 190271.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 1
Initial Penalty: $3,251.25
Current Penalty: $2,890.00
Issuance Date: 04/20/2012
Nr Instances: 2
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0728900
Contest Date:
Final Order: 05/04/2012
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/04/2012 | $2,890.00 | Serious | ||
Penalty | Z: Issued | 04/20/2012 | $3,251.25 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.219(d)(1): Pulley(s) with part(s) seven feet or less from the floor or work platform were not guarded in accordance with the requirements specified in 29 CFR 1910.219(m) and (o): 101 W. Railroad St., Morrill, NE 69358 (Shop Area, Texture Line Area): The employer did not ensure that pulleys were adequately guarded on both the Curtis St. Louis Air Compressor and the Sewing Conveyor.