Violation Detail
Standard Cited: 19100119 J02 Process safety management of highly hazardous chemicals.
Inspection Nr: 1521774.015
Citation: 01015
Citation Type: Serious
Abatement Date: 08/03/2022 4
Initial Penalty: $13,653.00
Current Penalty: $13,653.00
Issuance Date: 11/08/2021
Nr Instances: 1
Nr Exposed: 25
Related Event Code (REC):
Gravity: 10
Report ID: 0215300
Contest Date: 12/01/2021
Final Order: 08/15/2022
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 08/15/2022 | $13,653.00 | 08/03/2022 | Serious | |
Penalty | C: Contested | 12/06/2021 | $13,653.00 | 08/03/2022 | Serious | |
Penalty | Z: Issued | 11/08/2021 | $13,653.00 | 08/03/2022 | Serious |
Text For Citation: 01 Item/Group: 015 Hazard:
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going integrity of process equipment: a) On or about May 12, 2021, at Limetree Bay Refining, LLC., Delayed Coker Unit (DCU) - The employer failed to establish and implement written procedures to maintain the on-going integrity of process equipment. Specifically, the employer's written procedures for the inspection of pressure vessels, 69-60100 "PRESSURE VESSEL INSPECTION" did not include written procedures for inspecting insulated pressure vessels for Corrosion Under Insulation (CUI). Failure to address CUI on insulated equipment could result in unidentified, unmitigated corrosion leading to vessel failure and loss of containment, exposing employees to fire, toxic, and explosion hazards.