Violation Detail
Standard Cited: 19260454 B Training requirements.
Inspection Nr: 1430100.015
Citation: 01007
Citation Type: Serious
Abatement Date: 04/20/2020 5
Initial Penalty: $2,892.00
Current Penalty: $2,892.00
Issuance Date: 03/04/2020
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 5
Report ID: 0420600
Contest Date:
Final Order: 04/27/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 03/04/2020 | $2,892.00 | 04/20/2020 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1926.454(b): The employer did not have each employee involved in erecting, disassembling, moving, operating, repairing, maintaining, or inspecting a scaffold trained by a competent person to recognize any hazards associated with the work in question. a) On or about September 10, 2019 and prior to that time, at the south side of the commercial building, the supported scaffold was erected, disassemble and altered by employees who were not trained by a qualified competent person. The scaffold was disassemble while workers where working from it on lower levels and portions of the fall protection were removed while workers were applying stucco, exposing them to fall and struck-by hazards.