Violation Detail
Standard Cited: 19260417 B Lockout and tagging of circuits.
Inspection Nr: 1421295.015
Citation: 02001B
Citation Type: Other
Abatement Date: 12/30/2019 2
Initial Penalty: $5,304.00
Current Penalty: $0.00
Issuance Date: 11/26/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0626600
Contest Date: 12/26/2019
Final Order: 01/09/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 01/09/2021 | $0.00 | 12/30/2019 | Other | |
Penalty | C: Contested | 12/26/2019 | $5,304.00 | 12/03/2019 | Serious | |
Penalty | Z: Issued | 11/26/2019 | $5,304.00 | 12/03/2019 | Serious |
Text For Citation: 02 Item/Group: 001B Hazard:
29 CFR 1926.417(b): Equipment or circuits that were de-energized were not rendered inoperative: On or about August 6, 2019 at the Square D breaker box, employees were exposed to electrical hazards when the circuit breaker to room E-207 was not rendered inoperative.