Violation Detail
Standard Cited: 19100119 D Process safety management of highly hazardous chemicals.
Inspection Nr: 1417086.015
Citation: 01007A
Citation Type: Serious
Abatement Date: 03/04/2020 2
Initial Penalty: $13,260.00
Current Penalty: $10,621.00
Issuance Date: 01/15/2020
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC): A;R
Gravity: 10
Report ID: 0522000
Contest Date: 02/14/2020
Final Order: 10/25/2021
Emphasis:
Substance: 0730
Substance: 0926
Substance: 0990
Substance: 1040
Substance: 1380
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 10/25/2021 | $10,621.00 | 03/04/2020 | Serious | |
Penalty | C: Contested | 02/14/2020 | $13,260.00 | 03/04/2020 | Serious | |
Penalty | Z: Issued | 01/15/2020 | $13,260.00 | 03/04/2020 | Serious |
Text For Citation: 01 Item/Group: 007A Hazard:
29 CFR 1910.119(d): Process safety information. In accordance with the schedule set forth in paragraph (e)(1) of this section, the employer shall complete a compilation of written process safety information before conducting any process hazard analysis required by the standard. The compilation of written process safety information is to enable the employer and the employees involved in operating the process to identify and understand the hazards posed by those processes involving highly hazardous chemicals. This process safety information shall include information pertaining to the hazards of the highly hazardous chemicals used or produced by the process, information pertaining to the technology of the process, and information pertaining to the equipment in the process. (a) On or about July 22, 2019, the employer did not compile written process safety information pertaining to the hazards of manufacturing small arms ammunition, such as but not limited to a block flow diagram, electrical schematics for the building, and information regarding the use of magazines for storage of gun powder and primers.