Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1416622.015
Citation: 01001
Citation Type: Other
Abatement Date: 03/05/2020 2
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 01/15/2020
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): A
Gravity:
Report ID: 0626000
Contest Date:
Final Order: 02/05/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/05/2020 | $13,260.00 | 03/05/2020 | Other | |
Penalty | Z: Issued | 01/15/2020 | $13,260.00 | 02/11/2020 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedures did not clearly and specifically outline the steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy. The employer did not provide an adequate Lockout/Tagout procedure for the changing of an air compressor pressure switch. AVD Changed due to Informal Settlement Agreement: The employer did not develop a written Lockout/Tagout procedure for the Speedair (model: 35Wc55) air compressor.