Violation Detail
Standard Cited: 19100303 G01 I C General.
Inspection Nr: 1407005.015
Citation: 02016
Citation Type: Serious
Abatement Date: 12/19/2019 2
Initial Penalty: $4,376.00
Current Penalty: $2,625.60
Issuance Date: 10/31/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 1
Report ID: 0112000
Contest Date: 11/27/2019
Final Order: 03/27/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 03/27/2020 | $2,625.60 | 12/19/2019 | Serious | |
Penalty | F: Formal Settlement | 03/27/2020 | $2,625.60 | 12/19/2019 | Serious | |
Penalty | C: Contested | 12/05/2019 | $4,376.00 | 12/19/2019 | Serious | |
Penalty | Z: Issued | 10/31/2019 | $4,376.00 | 12/19/2019 | Serious |
Text For Citation: 02 Item/Group: 016 Hazard:
29 CFR 1910.303(g)(1)(i)(C): For electric equipment operating at 600 volts, nominal, or less to ground, and likely to require examination, adjustment, servicing, or maintenance while energized, the work space was not clear and did not extend from the grade, floor, or platform to the height required by paragraph (g)(1)(vi) of 29 CFR 1910.303. Other equipment associated with the electrical installation extended more than 153 mm (6 in.) beyond the front of the electric equipment: Block Plant: On, or about, June 18, 2019, a Dongan transformer was located in the working space for the I-T-E 120/208 volt panelboard.