Standard Cited: 19100147 D03 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1406641.015
Citation: 01004A
Citation Type: Serious
Abatement Date: 10/29/2019 2
Initial Penalty: $13,260.00
Current Penalty: $13,260.00
Issuance Date: 09/13/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0419400
Contest Date:
Final Order: 10/15/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 09/13/2019 | $13,260.00 | 10/29/2019 | Serious |
Text For Citation: 01 Item/Group: 004A Hazard:
29 CFR 1910.147(d)(3): All energy isolating devices that were needed to control the energy to the machine or equipment were not physically located and operated in such a manner as to isolate the machine or equipment from the energy source(s): (a) SPM Machine - On or about June 7, 2019 the employer allowed employees to get inside the SPM machines without physically locating and operating all energy isolation devices for the machine exposing them to caught in hazards .