Violation Detail
Standard Cited: 19260417 B Lockout and tagging of circuits.
Inspection Nr: 1395386.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 1
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 05/10/2019
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 1
Report ID: 0936200
Contest Date:
Final Order: 06/10/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/10/2019 | $0.00 | Serious | ||
Penalty | Z: Issued | 05/10/2019 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1926.417(b): Equipment or circuits that were de-energized were not rendered inoperative: Electrical Room #1101: Employee(s) were performing bathroom renovation activities, such as upgrading the electrical system. At the time of the inspection, the breaker panel supplying power to the bathroom was disconnected but not secured to prevent re-energizing. Employees were exposed to electrical shock hazards of 120 volts.