Standard Cited: 19100147 C07 I B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1382880.015
Citation: 01003
Citation Type: Serious
Abatement Date: 08/26/2019 2
Initial Penalty: $6,251.00
Current Penalty: $6,251.00
Issuance Date: 08/12/2019
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 1
Report ID: 0523900
Contest Date: 09/05/2019
Final Order: 09/27/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 09/27/2021 | $6,251.00 | 08/26/2019 | Serious | |
Penalty | C: Contested | 09/09/2019 | $6,251.00 | 08/26/2019 | Serious | |
Penalty | Z: Issued | 08/12/2019 | $6,251.00 | 08/26/2019 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(7)(i)(B): Affected employees were not instructed in the purpose and use of the energy control procedure: (a) Throughout the production area; Affected employees were not instructed in the purpose and use of energy control (lockout) procedures.