Violation Detail
Standard Cited: 19100303 B01 IV General.
Inspection Nr: 1377997.015
Citation: 01011
Citation Type: Other
Abatement Date: 01/11/2021 2
Initial Penalty: $8,335.00
Current Penalty: $8,000.00
Issuance Date: 07/30/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0728500
Contest Date: 08/19/2019
Final Order: 05/11/2020
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/11/2020 | $8,000.00 | 01/11/2021 | Other | |
Penalty | C: Contested | 08/21/2019 | $8,335.00 | 09/03/2019 | Serious | |
Penalty | Z: Issued | 07/30/2019 | $8,335.00 | 09/03/2019 | Serious |
Text For Citation: 01 Item/Group: 011 Hazard:
29 CFR 1910.303(b)(1)(iv): Electric equipment was not free from recognized hazards that were likely to cause serious physical harm to employees, such as damaged electrical insulation: The employer is failing to protect employees from possible shock , burns or potential electrocution, associated to using damaged electrical equipment. This was most recently documented on February 12, 2019 at a worksite located at 1078 S Jefferson Ave, Lebanon, Missouri. Employees in the Heading Department working on the defect line were exposed to serious injuries from possible shock , burns or potential electrocution, in that the power cord was found with damaged outer insulation.