Violation Detail
Standard Cited: 19100303 B07 IV General.
Inspection Nr: 1375672.015
Citation: 01012A
Citation Type: Serious
Abatement Date: 1
Initial Penalty: $3,832.00
Current Penalty: $1,916.00
Issuance Date: 06/07/2019
Nr Instances: 3
Nr Exposed: 10
Related Event Code (REC):
Gravity: 5
Report ID: 0112000
Contest Date:
Final Order: 07/09/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/09/2019 | $1,916.00 | Serious | ||
Penalty | Z: Issued | 06/07/2019 | $3,832.00 | Serious |
Text For Citation: 01 Item/Group: 012A Hazard:
29 CFR 1910.303(b)(7)(iv): Electric equipment had damaged parts that may adversely affect safe operation or mechanical strength of the equipment, such as parts that are broken, bent, cut, or deteriorated by corrosion, chemical action, or overheating: A. Maintenance Shop: On, or about, February 13, 2019, the power cord was damaged on the SawStop table saw. B. Building 3, Line 4: On, or about, February 13, 2019, the power cord that was provided for speed control box was damaged. C. Building 3, Line 4: On, or about, February 13, 2019, the power cord for the take-up unit was damaged.