Standard Cited: 19100029 B01 Fall protection systems and falling object protection-criteria and practices.
Inspection Nr: 1375672.015
Citation: 01002B
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 06/07/2019
Nr Instances: 5
Nr Exposed: 4
Related Event Code (REC):
Gravity: 5
Report ID: 0112000
Contest Date:
Final Order: 07/09/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/09/2019 | $0.00 | Serious | ||
Penalty | Z: Issued | 06/07/2019 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 002B Hazard:
29 CFR 1910.29(b)(1): The top edge height of top rails, or equivalent guardrail system members, was not 42 inches, plus or minus 3 inches, above the walking-working surface: A. Environmental Area: On, or about, March 14, 2019, the top rail of the guardrail system provided on the Final Neutralization tank platform was measured to be 36 inches above the work platform. B. Environmental Area, Old Pit: On, or about, March 14, 2019, the top rail of the guardrail system provided on the stairway opening to the lower level was measured to be 37 inches above the floor. C. Environmental Area, New Pit: On, or about, March 14, 2019, the top rail of the guardrail system provided on the stairway opening to the lower level was measured to be 34.5 inches above the floor. D. Environmental Area, Old Pit, Lower Level: On, or about, March 14, 2019, a single railing was provided at the end of the work platform. The railing was 32 inches above the platform and no midrail was provided. E. Environmental Settling Tanks: The guardrails provided for the walkover bridge above the flock and clarifier chambers had a top rail that was 32.5 inches above the platform.