Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 1373448.015
Citation: 01007
Citation Type: Serious
Abatement Date: 08/10/2019 2
Initial Penalty: $3,978.00
Current Penalty: $2,784.60
Issuance Date: 04/23/2019
Nr Instances: 3
Nr Exposed: 4
Related Event Code (REC):
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 06/02/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | P: Petition to Mod Abatement | $2,784.60 | 08/10/2019 | Serious | ||
Penalty | I: Informal Settlement | 06/02/2019 | $2,784.60 | 06/10/2019 | Serious | |
Penalty | Z: Issued | 04/23/2019 | $3,978.00 | 06/10/2019 | Serious |
Text For Citation: 01 Item/Group: 007 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: A. Wash Area: On, or about, January 24, 2019, approximately thirteen circuit breakers that were located in an Eaton wall mounted panelboard were not labeled to indicate their purpose. The circuit breakers were in the on position. B. Receiving Dock: On, or about, January 24, 2019, approximately three circuit breakers that were located in Panel P2 were not labeled to indicate their purpose. C. Receiving Dock: On, or about, January 24, 2019, approximately 20 circuit breakers that were located in Panel P2A were not labeled to indicate their purpose.