Violation Detail
Standard Cited: 19100147 C04 II B The control of hazardous energy (lockout/tagout).
Inspection Nr: 1360216.015
Citation: 01002
Citation Type: Serious
Abatement Date: 02/27/2019 2
Initial Penalty: $10,627.00
Current Penalty: $7,438.90
Issuance Date: 02/07/2019
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): R
Gravity: 5
Report ID: 0418300
Contest Date:
Final Order: 03/06/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/06/2019 | $7,438.90 | 02/27/2019 | Serious | |
Penalty | Z: Issued | 02/07/2019 | $10,627.00 | 02/27/2019 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.147(c)(4)(ii)(B): The energy control procedure did not clearly and specifically specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy: (a) On or about 11/08/2018 - Cement Lining Department, procedures did not specify how to prevent movement of the mixer paddles for employees cleaning inside the Cement Mixer machine.