Violation Detail
Standard Cited: 19260403 E General requirements.
Inspection Nr: 1358480.015
Citation: 01004B
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 03/19/2019
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC):
Gravity: 5
Report ID: 0524500
Contest Date:
Final Order: 04/16/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/16/2019 | $0.00 | Serious | ||
Penalty | Z: Issued | 03/19/2019 | $0.00 | Serious |
Text For Citation: 01 Item/Group: 004B Hazard:
29 CFR 1926.403(e): All splices and joints and free ends of conductors were not covered with insulation equivalent to that of the conductors or with an insulating device designed for the purpose: On or about November 6, 2018, employees using circular saws and other electric power tools were exposed to electric shock hazards and the employer did not ensure that the damaged cord sets and power tool cords were repaired with insulation equivalent to that of the original equipment.