Standard Cited: 19100180 H03 III B Crawler locomotive and truck cranes.
Inspection Nr: 1347790.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 02/13/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 01/17/2019
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0627510
Contest Date:
Final Order: 02/14/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | Z: Issued | 01/17/2019 | $0.00 | 02/13/2019 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.180(h)(3)(iii)(b): During hoisting, care was not taken to ensure that the load did not contact any obstructions. On or about September 19, 2018 at Well #LHS1704BH the employer failed to ensure that the load being hoisted by a QMC hydraulic truck crane did not come in contact with an obstruction while dismantling a pumping unit.