Standard Cited: 19100305 G01 IV A Wiring methods, components, and equipment for general use.
Inspection Nr: 1331625.015
Citation: 02003
Citation Type: Other
Abatement Date: 05/15/2019 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/27/2018
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity:
Report ID: 0418100
Contest Date:
Final Order: 04/04/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/04/2019 | $0.00 | 05/15/2019 | Other | |
Penalty | Z: Issued | 12/27/2018 | $0.00 | 01/24/2019 | Other |
Text For Citation: 02 Item/Group: 003 Hazard:
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: a) Shop - On or about 07/16/18 and at times prior thereto employees operated the Notcher Machine #1. The electrical flexible cables running between the two electrical boxes (on the side of the machine) were not installed and protected inside a conduit. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).