Violation Detail
Standard Cited: 19100219 D01 Mechanical power-transmission apparatus.
Inspection Nr: 1315637.015
Citation: 01009
Citation Type: Serious
Abatement Date: 11/30/2018 2
Initial Penalty: $10,975.00
Current Penalty: $6,036.00
Issuance Date: 11/02/2018
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 5
Report ID: 0418600
Contest Date:
Final Order: 11/30/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 11/30/2018 | $6,036.00 | 11/30/2018 | Serious | |
Penalty | Z: Issued | 11/02/2018 | $10,975.00 | 11/30/2018 | Serious |
Text For Citation: 01 Item/Group: 009 Hazard:
29 CFR 1910.219(d)(1): Pulley(s) with part(s) seven feet or less from the floor or work platform were not guarded in accordance with the requirements specified in 29 CFR 1910.219(m) and (o): a) At Fab / Rebar Shop: On or about May 9, 2018 and at times prior; the employer allowed his employees to perform maintenance and servicing on the shear line motor with an exposed 1800 rpm pulley exposing employees to caught-by hazards.