Violation Detail
Standard Cited: 19260062 L01 I Lead
Inspection Nr: 1312070.015
Citation: 01002C
Citation Type: Serious
Abatement Date: 10/10/2018 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 08/22/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 5
Report ID: 0112000
Contest Date: 09/17/2018
Final Order: 04/25/2019
Emphasis:
Substance: 1591
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 04/25/2019 | $0.00 | 10/10/2018 | Serious | |
Penalty | C: Contested | 09/19/2018 | $0.00 | 10/10/2018 | Serious | |
Penalty | Z: Issued | 08/22/2018 | $0.00 | 10/10/2018 | Serious |
Text For Citation: 01 Item/Group: 002C Hazard:
29 CFR 1926.62(l)(1)(i): The employer did not ensure that at least the following Lead hazards were communicated to employee(s): reproductive/developmental toxicity; central nervous system effects; kidney effects; blood effects; and acute toxicity effects. PONEMAH MILL, 611 NORWICH AVENUE, TAFTVILLE, CT: On or about and at times prior to April 27, 2018, employees and subcontractors working at an old mill (circa 1860s) were not provided with information regarding the hazards of lead exposure. The employer was the General Contractor for the site and had general supervisory authority over the worksite. Paint that was peeling from the walls was analyzed at the Salt Lake Technical Center and was determined to be positive for lead.