Violation Detail
Standard Cited: 19100303 B01 General.
Inspection Nr: 1307935.015
Citation: 01003
Citation Type: Serious
Abatement Date: 10/11/2018 2
Initial Penalty: $6,467.00
Current Penalty: $3,033.00
Issuance Date: 09/14/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0418100
Contest Date:
Final Order: 10/04/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 10/04/2018 | $3,033.00 | 10/11/2018 | Serious | |
Penalty | Z: Issued | 09/14/2018 | $6,467.00 | 10/11/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.303(b)(1): Electrical equipment was not free from recognized hazards that were likely to cause death or serious physical harm to employees: a) Site - On or about 04/10/18 and at times prior thereto employees assigned to the installation of a coolant expansion tank powered portable tools with a make-shift extension cord built with a metallic 110V four-outlet receptacle box in the female connection side. The box cover was loose, and the live terminals were exposed. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).