Violation Detail
Standard Cited: 19261408 A02 III B
Inspection Nr: 1287795.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 06/15/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): R
Gravity: 10
Report ID: 0216000
Contest Date:
Final Order: 07/16/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/16/2018 | $12,934.00 | Serious | ||
Penalty | Z: Issued | 06/15/2018 | $12,934.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.1408(a)(2)(iii)(B): The employer did not determine if any part of the equipment, load line or load (including rigging and lifting accessories), while operating up to the equipment's maximum working radius in the work zone, could get closer than the minimum approach distance of the power line permitted under Table A (see �� 1926.1408). If so, then the employer must follow the requirements in paragraph (b) of this section to ensure that no part of the equipment, load line, or load (including rigging and lifting accessories), gets closer to the line than the minimum approach distance: On or about: 1/11/2018 Location: 5 Secor Lane Pelham NY; overhead street electrical utility conductors a) The employer did not maintain the minimum clearance to avoid electrical contact when using TADANO rough terrain crane near overhead electric utility conductors to prevent a electric shock hazard (approx. 2.3 kV).