Violation Detail
Standard Cited: 19100107 E02 Spray finishing using flammable and combustible materials.
Inspection Nr: 1285980.015
Citation: 01003
Citation Type: Serious
Abatement Date: 03/21/2018 2
Initial Penalty: $4,991.00
Current Penalty: $3,300.00
Issuance Date: 02/23/2018
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 1
Report ID: 0418100
Contest Date:
Final Order: 03/16/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 03/16/2018 | $3,300.00 | 03/21/2018 | Serious | |
Penalty | Z: Issued | 02/23/2018 | $4,991.00 | 03/21/2018 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.107(e)(2): The quantity of flammable or combustible liquids kept in the vicinity of spraying operations were not at a minimum required for operations or they exceeded a supply for one day or one shift: Maaco Collision Repair and Auto Paint, Sugar Hill, GA - Employees were exposed to a fire hazard. On or about 12/12/17, and times prior to, there were three 55 gallon drum of paint reducer, several 5 gallon cans of waste paint (flammable and/or combustible liquids), and several 1 gallon cans of paint in the shop area that was outside of an inside storage cabinet. In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).