Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1283359.015
Citation: 01001A
Citation Type: Serious
Abatement Date: 04/19/2018 2
Initial Penalty: $12,675.00
Current Penalty: $8,870.00
Issuance Date: 03/22/2018
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC): R
Gravity: 10
Report ID: 0111400
Contest Date:
Final Order: 04/12/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 04/12/2018 | $8,870.00 | 04/19/2018 | Serious | |
Penalty | Z: Issued | 03/22/2018 | $12,675.00 | 04/19/2018 | Serious |
Text For Citation: 01 Item/Group: 001A Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section: Location: Production Room Instance A: Cord-and-plug connected equipment such as the Oshikiri Molder were not rendered safe by disconnecting the cord and having it under the exclusive control of the employee maintaining that equipment. Instance B: Hard wired equipment such as the Fritsch Laminator, the Capway oven and the Spiral dough mixers were not locked out prior to employees maintaining the equipment. Instance C: Written procedures had not been developed for the Capway oven. Instance D: Written procedures for the Fritsch Line did not include procedures for controlling pneumatic energy.