Violation Detail
Standard Cited: 19100107 D03 Spray finishing using flammable and combustible materials.
Inspection Nr: 1281130.015
Citation: 01006
Citation Type: Serious
Abatement Date: 07/16/2018 2
Initial Penalty: $4,989.00
Current Penalty: $2,993.40
Issuance Date: 04/11/2018
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 1
Report ID: 0626700
Contest Date:
Final Order: 05/01/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 05/01/2018 | $2,993.40 | 07/16/2018 | Serious | |
Penalty | Z: Issued | 04/11/2018 | $4,989.00 | 05/16/2018 | Serious |
Text For Citation: 01 Item/Group: 006 Hazard:
29 CFR 1910.107(d)(3): The spray booth did not have an independent exhaust duct system discharging to the exterior of the building: a) Inside the blasting and painting building, where the spray painting room exhaust system was not independent of the paint mixing room exhaust system.