Violation Detail
Standard Cited: 19260651 K02 Specific Excavation Requirements.
Inspection Nr: 1269327.015
Citation: 02001A
Citation Type: Willful
Abatement Date: 04/10/2018 4
Initial Penalty: $129,336.00
Current Penalty: $129,336.00
Issuance Date: 03/15/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0830300
Contest Date: 03/30/2018
Final Order: 10/01/2019
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | W: Empr Withdrew | 10/01/2019 | $129,336.00 | 04/10/2018 | Willful | |
Penalty | C: Contested | 04/04/2018 | $129,336.00 | 04/10/2018 | Willful | |
Penalty | Z: Issued | 03/15/2018 | $129,336.00 | 04/10/2018 | Willful |
Text For Citation: 02 Item/Group: 001A Hazard:
29 CFR 1926.651(k)(2): Where the competent person found evidence of a situation that could result in possible cave-in, indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions, exposed employee(s) was/were not removed from the hazardous area until the necessary precautions have been taken to ensure their safety: (a) On or about October 3, 2017 where the employees were exposed to trench crushing hazards while attempting to install a water line at a depth of eight feet where flowing water was eroding the trench walls and collapsing protective systems in the vicinity of First Street SW and Troy Avenue Tappen, ND.