Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1268712.015
Citation: 01003
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $5,174.00
Current Penalty: $2,500.00
Issuance Date: 04/02/2018
Nr Instances: 1
Nr Exposed: 93
Related Event Code (REC):
Gravity: 5
Report ID: 0134000
Contest Date: 04/25/2018
Final Order: 06/25/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/25/2018 | $2,500.00 | Serious | ||
Penalty | C: Contested | 04/25/2018 | $5,174.00 | Serious | ||
Penalty | Z: Issued | 04/02/2018 | $5,174.00 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: Location: Facility On or about October 6, 2017, the employer did not perform a periodic inspection of the energy control procedures on an annual basis as required.