Violation Detail
Standard Cited: 19100333 B02 Selection and use of work practices
Inspection Nr: 1251758.015
Citation: 01013
Citation Type: Serious
Abatement Date: 01/25/2018 2
Initial Penalty: $6,972.00
Current Penalty: $3,486.00
Issuance Date: 12/28/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0418400
Contest Date:
Final Order: 01/19/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/19/2018 | $3,486.00 | 01/25/2018 | Serious | |
Penalty | Z: Issued | 12/28/2017 | $6,972.00 | 01/25/2018 | Serious |
Text For Citation: 01 Item/Group: 013 Hazard:
29 CFR 1910.333(b)(2): While an employee was exposed to contact with parts of fixed electric equipment or circuits which were deenergized, the circuits energizing the parts were not locked out or tagged or both in accordance with the requirements of this paragraph (b) of 29 CFR 1910.333(b)(2): (a) Receiving Shed, on or about and at times preceding to August 1, 2017, during de-energizing procedures, the main power was disconnected and the fuses to the disconnect were removed.