Violation Detail
Standard Cited: 19100147 F01 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1238757.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 12/05/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 11/22/2017
Nr Instances: 2
Nr Exposed: 8
Related Event Code (REC): R
Gravity: 10
Report ID: 0523400
Contest Date:
Final Order: 12/13/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/13/2017 | $0.00 | 12/05/2017 | Serious | |
Penalty | Z: Issued | 11/22/2017 | $0.00 | 12/05/2017 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(f)(1)(ii): When lockout devices were temporarily removed from the energy isolating device and the machine, or equipment was energized to test and position the machine, the employees were not removed from the machine or equipment area in accordance with the paragraph (e)(2): (a) Heidelberg Speedmaster Six (6) Color Model SPL 102 printing press : The employer did not insure that employees were removed from the machine hazard area during testing and machine positioning for setup.