Violation Detail
Standard Cited: 19100303 B01 IV General.
Inspection Nr: 1214986.015
Citation: 01005A
Citation Type: Serious
Abatement Date: 09/05/2017 2
Initial Penalty: $5,079.00
Current Penalty: $3,000.00
Issuance Date: 08/09/2017
Nr Instances: 2
Nr Exposed: 3
Related Event Code (REC): C
Gravity: 1
Report ID: 0418100
Contest Date:
Final Order: 08/25/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/25/2017 | $3,000.00 | 09/05/2017 | Serious | |
Penalty | Z: Issued | 08/09/2017 | $5,079.00 | 09/05/2017 | Serious |
Text For Citation: 01 Item/Group: 005A Hazard:
29 CFR 1910.303(b)(1)(iv): Safety of equipment was not determined using considerations for electrical insulation On or about March 2, 2017, employees were exposed to electrical hazards. Employees walk and work at the presses where these damaged electrical cords were found. Employees plug the cords into outlets. a. Extension cord: outer plastic insulator was damaged. b. Extension cord: damaged cord had been repaired with electrical tape in two locations In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).