Violation Detail
Standard Cited: 19100269 R01 IV Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1192989.015
Citation: 01003
Citation Type: Serious
Abatement Date: 03/24/2017
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 03/07/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 10
Report ID: 0626700
Contest Date: 03/28/2017
Final Order: 07/18/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/18/2018 | $0.00 | 03/24/2017 | Serious | |
Penalty | C: Contested | 03/28/2017 | $12,675.00 | 03/24/2017 | Serious | |
Penalty | Z: Issued | 03/07/2017 | $12,675.00 | 03/24/2017 | Serious |
Text For Citation: 01 Item/Group: 003 Hazard:
29 CFR 1910.269(r)(1)(iv): Branches that were contacting exposed energized conductors or equipment or that were within the distances specified in Table R-5, Table R-6, Table R-7, and Table R-8 were not removed only through the use of insulating equipment: a) At 7020 Firethorn Drive, Beaumont, TX, the branches within the minimum approach distance were not removed with insulated equipment, exposing employees to electrical hazards.