Standard Cited: 19100269 R01 I Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1192989.015
Citation: 01001
Citation Type: Other
Abatement Date: 08/06/2018 2
Initial Penalty: $12,675.00
Current Penalty: $10,140.00
Issuance Date: 03/07/2017
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity:
Report ID: 0626700
Contest Date: 03/28/2017
Final Order: 07/18/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 07/18/2018 | $10,140.00 | 08/06/2018 | Other | |
Penalty | C: Contested | 03/28/2017 | $12,675.00 | 03/24/2017 | Serious | |
Penalty | Z: Issued | 03/07/2017 | $12,675.00 | 03/24/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(r)(1)(i): Before an employee climbed, entered, or worked around any tree, a determination was not made of the nominal voltage of electric power lines posing a hazard to employees: a) At 7020 Firethorn Drive, Beaumont, TX, the nominal voltage of electric power lines was not determined prior to start of work, exposing employees to electrical hazards.