Violation Detail
Standard Cited: 19100147 D06 The control of hazardous energy (lockout/tagout).
Inspection Nr: 1180433.015
Citation: 01001B
Citation Type: Serious
Abatement Date: 03/03/2017 2
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 02/07/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 10
Report ID: 0627500
Contest Date:
Final Order: 02/24/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/24/2017 | $0.00 | 03/03/2017 | Serious | |
Penalty | Z: Issued | 02/07/2017 | $12,675.00 | 02/27/2017 | Serious |
Text For Citation: 01 Item/Group: 001B Hazard:
29 CFR 1910.147(d)(6): Prior to starting work on machines or equipment that had been locked out or tagged out, the authorized employee did not verify that isolation and deenergization of the machine or equipment had been accomplished: Amine Unit: On or about September 26, 2016 prior to starting maintenance on P-0116S the authorized employee did not verify that all potentially hazardous energy was not relieved on pump P-0116A after the application of lockout tagout devices. This condition exposed employees to a burn hazard.