Standard Cited: 19100107 D02 Spray finishing using flammable and combustible materials.
Inspection Nr: 1149264.015
Citation: 01002
Citation Type: Serious
Abatement Date: 08/26/2016 2
Initial Penalty: $2,520.00
Current Penalty: $2,520.00
Issuance Date: 07/29/2016
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC): C
Gravity: 5
Report ID: 0636900
Contest Date:
Final Order: 08/15/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/15/2016 | $2,520.00 | 08/26/2016 | Serious | |
Penalty | Z: Issued | 07/29/2016 | $2,520.00 | 08/26/2016 | Serious |
Text For Citation: 01 Item/Group: 002 Hazard:
29 CFR 1910.107(d)(2): Mechanical ventilation was not kept in operation at all times while spraying operations were being conducted and for a sufficient time thereafter to allow vapors from drying coated articles and drying finishing material residue to be exhausted. In the tire and wheel production paint booth, the employer did not ensure that mechanical ventilation was operational and maintained exposing employees to respiratory health hazards.