Violation Detail
Standard Cited: 19100217 E01 I A Mechanical power presses.
Inspection Nr: 1148175.015
Citation: 01008B
Citation Type: Serious
Abatement Date: 09/13/2016 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 07/27/2016
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity: 1
Report ID: 0112000
Contest Date:
Final Order: 08/16/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 08/16/2016 | $0.00 | 09/13/2016 | Serious | |
Penalty | Z: Issued | 07/27/2016 | $0.00 | 09/13/2016 | Serious |
Text For Citation: 01 Item/Group: 008B Hazard:
29 CFR 1910.217(e)(1)(i)(A): Periodic and regular inspections of each power press were not conducted to ensure that all of its parts, auxiliary equipment, and safeguards, including clutch/brake mechanism, anti-repeat feature, and single-stroke mechanism, are in safe operating condition and adjustment: Plant: On, or about, May 16, 2016, the company did not test presses on a weekly basis.