Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
Inspection Nr: 1146111.015
Citation: 03003
Citation Type: Other
Abatement Date: 07/07/2017 2
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 10/27/2016
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC):
Gravity:
Report ID: 0215800
Contest Date: 11/10/2016
Final Order: 08/17/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 08/17/2017 | $0.00 | 07/07/2017 | Other | |
Penalty | C: Contested | 11/30/2016 | $0.00 | 11/08/2016 | Other | |
Penalty | Z: Issued | 10/27/2016 | $0.00 | 11/08/2016 | Other |
Text For Citation: 03 Item/Group: 003 Hazard:
29 CFR 1910.219(c)(4)(i): Unguarded projecting shaft end(s) projected more than one half the diameter of the shaft: a) On or about 6/7/2016, Base of storage tower: A shaft end was not guarded at the base of the access ladder. Abatement certification is required for these items.