Violation Detail
Standard Cited: 19100219 D01 Mechanical power-transmission apparatus.
Inspection Nr: 1134720.015
Citation: 02001
Citation Type: Serious
Abatement Date: 08/19/2016 2
Initial Penalty: $24,693.00
Current Penalty: $9,800.00
Issuance Date: 08/09/2016
Nr Instances: 1
Nr Exposed: 4
Related Event Code (REC):
Gravity: 10
Report ID: 0626300
Contest Date:
Final Order: 09/06/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/06/2016 | $9,800.00 | 08/19/2016 | Serious | |
Penalty | Z: Issued | 08/09/2016 | $24,693.00 | 08/19/2016 | Repeat |
Text For Citation: 02 Item/Group: 001 Hazard:
29 CFR 1910.219(d)(1): Pulley(s) with part(s) seven feet or less from the floor or work platform were not guarded in accordance with the requirements specified in 29 CFR 1910.219(m) and (o): (a) In the Mahard Egg Farm Inc. grinding room where a guard was missing on a pulley.