Violation Detail
Standard Cited: 19100254 D09 III Arc welding and cutting.
Inspection Nr: 1102760.015
Citation: 01004
Citation Type: Serious
Abatement Date: 01/21/2016 2
Initial Penalty: $4,000.00
Current Penalty: $3,000.00
Issuance Date: 12/23/2015
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0316300
Contest Date:
Final Order: 01/19/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/19/2016 | $3,000.00 | 01/21/2016 | Serious | |
Penalty | Z: Issued | 12/23/2015 | $4,000.00 | 01/21/2016 | Serious |
Text For Citation: 01 Item/Group: 004 Hazard:
29 CFR 1910.254(d)(9)(iii): Cables with damaged insulation or exposed bare conductors were not replaced: a) Orbital ATK, Inc. dba New River Energetics, Army Radford Ammunition Plant Building 1513 Maintenance shop: On or about 09/29/2015, an electrode holder cable used in welding brackets was repaired with black tape in four different areas along the outer jacket of the cable and within 10 feet of the electrode holder to cover the exposed copper wires, thereby exposed an employee to a possible electrical shock. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.