Violation Detail
Standard Cited: 19100022 A03 General requirements.
Inspection Nr: 1100490.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 02/02/2016 2
Initial Penalty: $6,300.00
Current Penalty: $4,580.00
Issuance Date: 12/14/2015
Nr Instances: 50
Nr Exposed: 7
Related Event Code (REC):
Gravity: 10
Report ID: 0729300
Contest Date:
Final Order: 01/12/2016
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 01/12/2016 | $4,580.00 | 02/02/2016 | Serious | |
Penalty | Z: Issued | 12/14/2015 | $6,300.00 | 02/02/2016 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1910.22(a)(3): To facilitate cleaning, every floor, working place, and passageway were not kept free from protruding nails, splinters, holes, or loose boards: Inside of the Crunden Martin Facility, protruding sections of steel floor plate, loose wooden plywood, and deep depressions in the concrete floor were located at the following locations: a/ First floor by the main entrance. b/ First floor by Loading Dock #1. c/ Basement inside of the Otis Elevator #1. d/ Basement. e/ Second floor. f/ Third floor. g/ Fourth floor. h/ Fifth floor.